Larger buildings run on more than one voltage. Heavy equipment and lighting run at 480 or 277 volts, while transformers step power down to 208/120 volts for receptacles and office equipment. Empire Electric’s commercial electricians design, install and troubleshoot every part of that system.

Panels, feeders, transformers
480, 277, 208 and 120 volts
Loads spread across all three phases
Overheating, imbalance, trips
Most commercial buildings take power at 480Y/277 volts, feed heavy equipment and lighting directly, and use step-down transformers to create 208Y/120 volts for everything else.
Pick a piece of equipment to see the voltage it needs and the path power takes to reach it.
A step-down transformer converts 480-volt power to 208Y/120 volts for receptacles, office equipment and smaller loads. Size it too small and it overheats; size it too large and you pay for capacity you’ll never use.
Estimate the step-down transformer for your 208Y/120-volt loads.
Estimate only: kVA = 208 V × amps × 1.732. Actual sizing follows an NEC load calculation, transformer overcurrent protection rules (NEC 450.3) and the design professional's specifications.
| Typical Home | Commercial Building | |
|---|---|---|
| Service voltage | 120/240V single-phase | 480Y/277V or 208Y/120V three-phase |
| Transformers | None in the building | Step-down transformers and separately derived systems |
| Panels | One main panel, maybe a sub-panel | Switchboards, distribution panels and multiple panelboards |
| Loads | Appliances and A/C | Motors, rooftop units, kitchens, servers and 277V lighting |
| Grounding | Single service ground | Bonding and grounding for every transformer secondary |
| Documentation | Basic panel labels | Panel schedules, one-line diagrams and arc-flash labels |
A great residential electrician may never have worked on a 480-volt switchboard or bonded a transformer secondary. Our commercial electricians do this every week, so we send them for every distribution job.
Panel layouts, feeder sizing and transformer selection, coordinated with your engineer or design-build.
New panelboards for tenant spaces, additions, equipment rooms and floors.
Step-down transformers installed, bonded, grounded and protected to code.
Loads spread evenly across phases to reduce heating and nuisance trips.
Power for rooftop units, compressors, kitchens, elevators and production equipment.
Accurate, up-to-date panel schedules and labels your facility team can rely on.
Our commercial troubleshooters find the cause, from a failing transformer to an overloaded phase.
We review the existing service, panels and loads, plus any drawings.
We plan panels, feeders and transformers, or build from your engineer’s plans.
We pull permits and coordinate shutdowns around your operations.
Our commercial crews install, terminate, bond, ground and label.
We verify voltages and rotation and update panel schedules.
Higher voltage like 480 volts moves large amounts of power efficiently to motors, rooftop units and lighting. Receptacles and office equipment need 120 volts, so step-down transformers create a 208Y/120-volt system for them.
It converts the building’s 480-volt power to 208Y/120 volts, creating a new electrical system that must be properly bonded, grounded and protected.
No. Commercial 208-volt power comes from a three-phase system. Equipment designed for 240 volts may run hotter or weaker on 208 volts, so we confirm ratings before connecting.
Uneven loads across phases can overheat transformers and neutrals and cause nuisance trips. We balance loads when installing and can rebalance existing panels.
Yes. We build from engineered plans, and we can also handle design-build for many tenant and equipment projects.
Yes. We troubleshoot, size and replace transformers and coordinate shutdowns to limit downtime.
Call or request a quote. Our commercial electricians will design, install or troubleshoot your panels and transformers.
(904) 365-7777
service@empireelec.com
5810 Macy Ave, Jacksonville, FL 32211
Mon–Fri, 8:00 am–4:00 pm · 24/7 emergency service